BHP-BHBE G16
290 MW generation in Campbell, WY · In queue since December 2021 · Proposed COD November 2024
290 MW
Capacity
1
Components
Wind
4y 5m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2024-11-15
BHP-BHBE G16 is a proposed wind generation project located in Campbell County, Wyoming. The project, with a total capacity of 290 MW, is being developed by BHP and is interconnected with Black Hills Power. It entered the transmission interconnection queue on December 14, 2021, and has a proposed commercial operation date of November 15, 2024. The project's interconnection agreement (IA) has been executed.
The project is located in the West region. The point of interconnection (POI) is the Pumpkin Buttes - Windstar Tap. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WY
County
Campbell
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Power
Entity
BHP
Service Type
—
Point of Interconnection
Pumpkin Buttes - Windstar Tap
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BHP-BHBE G16