BHP-BHBE G19
300 MW generation in Campbell, SD · In queue since May 2022 · Proposed COD December 2024
300 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-12-15
The proposed project BHP-BHBE G19 is a 300 MW solar generation project located in Campbell County, South Dakota, within the West region. The project is being developed by BHP and is interconnected with Black Hills Power. It entered the transmission interconnection queue on May 3, 2022, with a proposed commercial operation date of December 15, 2024. The interconnection agreement for the project has been executed.
The point of interconnection is the Windstar - Pumpkin Buttes 230 kV line. The project consists of 300 MW of solar photovoltaic generation capacity.
Generated from interconnection queue and public data sources
State
SD
County
Campbell
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Power
Entity
BHP
Service Type
—
Point of Interconnection
Windstar - Pumpkin Buttes 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BHP-BHBE G19