Project BHP-BHBE G21 — Project Summary

Queue ID
BHP-BHBE G21
Capacity
200 MW
Technology
Wind
Status
active
Location
Campbell, SD
Region
West
Developer
IA Status
IA Executed

BHP-BHBE G21

BHP-BHBE G21BetaActiveWindBHPLBNL

200 MW generation in Campbell, SD · In queue since August 2022 · Proposed COD November 2025

200 MW

Capacity

1

Components

Wind

3y 9m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection

Total Duration

3y 3m

Schedule

5 months past proposed COD

Construction75%
Queue EntryAug 23, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2025-11-30

About

The BHP-BHBE G21 project is a proposed 200 MW wind generation project located in Campbell County, South Dakota, within the West region. The project is being developed by BHP and is interconnected with Black Hills Power. It entered the transmission queue on August 23, 2022, with a proposed commercial operation date of November 30, 2025. The interconnection agreement (IA) for the project has been executed.

The point of interconnection (POI) for the project is the Pumpkin Buttes - Donkey Creek 230 kV line. The project consists of 200 MW of wind generation capacity. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

SD

County

Campbell

Grid Region

Mountain West

Market

Developer

Utility

Black Hills Power

Entity

BHP

Service Type

Point of Interconnection

Pumpkin Buttes - Donkey Creek 230 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BHP-BHBE G21