BPA-G0295
250 MW generation in Columbia, WA · In queue since October 2007 · Proposed COD December 2011
250 MW
Capacity
1
Components
Wind
18y 7m
In Queue
IA Executed
IA Status
COD target: 2011
Total Duration
4y 2m
Schedule
175 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2011-12-31
The proposed BPA-G0295 project is a 250 MW wind generation facility located in Columbia County, Washington. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an original queue entry date of October 26, 2007. Its proposed commercial operation date (COD) is December 31, 2011, and the interconnection agreement (IA) has been executed.
The project is composed entirely of wind generation, totaling the full 250 MW capacity. The point of interconnection (POI) for the project is the Central Ferry Substation.
Generated from interconnection queue and public data sources
State
WA
County
Columbia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Central Ferry Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN