BPA-G0344
488 MW generation in Gilliam, OR · In queue since September 2008 · Proposed COD April 2024
488 MW
Capacity
1
Components
Wind
17y 8m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
15y 7m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-30
The proposed BPA-G0344 project is a 488 MW wind generation facility located in Gilliam County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of September 4, 2008. The proposed commercial operation date is April 30, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Ashe-Marion 500kV #1 line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
OR
County
Gilliam
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ashe-Marion 500kV #1
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0344