Project BPA-G0344 — Project Summary

Queue ID
BPA-G0344
Capacity
488 MW
Technology
Wind
Status
active
Location
Gilliam, OR
Region
West
Developer
IA Status
Facility Study

BPA-G0344

BPA-G0344BetaActiveWindBPALBNL

488 MW generation in Gilliam, OR · In queue since September 2008 · Proposed COD April 2024

488 MW

Capacity

1

Components

Wind

17y 8m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection

Total Duration

15y 7m

Schedule

24 months past proposed COD

Facilities Study50%
Queue EntrySep 4, 2008

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-30

About

The proposed BPA-G0344 project is a 488 MW wind generation facility located in Gilliam County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of September 4, 2008. The proposed commercial operation date is April 30, 2024.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Ashe-Marion 500kV #1 line. The developer is not specified in the queue data.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Gilliam

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Ashe-Marion 500kV #1

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G0344