BPA-G0362
204 MW generation in Gilliam, OR · In queue since April 2009 · Proposed COD November 2012
204 MW
Capacity
1
Components
Wind
17y 1m
In Queue
Facility Study
IA Status
COD target: 2012
Total Duration
3y 7m
Schedule
164 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2012-11-01
The BPA-G0362 development project is a proposed 204 MW wind generation facility located in Gilliam County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of April 3, 2009. The proposed commercial operation date is November 1, 2012.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is a new substation near McNary 500 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Gilliam
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
New Substation near McNary 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0362