BPA-G0366
302 MW generation in Morrow, OR · In queue since May 2009 · Proposed COD November 2014
302 MW
Capacity
1
Components
Wind
17 years
In Queue
Facility Study
IA Status
COD target: 2014
Total Duration
5y 6m
Schedule
140 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2014-11-01
The proposed BPA-G0366 project is a 302 MW wind generation facility located in Morrow County, Oregon. The project, which consists of 302 MW of wind capacity, is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of May 19, 2009. The proposed commercial operation date is November 1, 2014.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is planned for a 230 kV substation on BPA's transmission system in Gilliam or Morrow County, Oregon, near or west of Boardman. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
A 230 kV substation on BPA's Transmission system in Gilliam or Morrow Co. Ore. near or west of Boardman
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0366