BPA-G0435
238 MW generation in Morrow, OR · In queue since August 2010 · Proposed COD November 2013
238 MW
Capacity
1
Components
Wind
15y 9m
In Queue
Facility Study
IA Status
COD target: 2013
Total Duration
3y 3m
Schedule
152 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2013-11-01
BPA-G0435 is a proposed wind generation project with a total capacity of 238 MW, located in Morrow County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of August 28, 2010. The proposed commercial operation date is November 1, 2013.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is a new substation on the 500 kV McNary-HPP Line.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
New substation on 500 kV McNary-HPP Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0435