BPA-G0501
1,100 MW generation in Klamath, OR · In queue since October 2014 · Proposed COD July 2018
1,100 MW
Capacity
1
Components
Gas
11y 7m
In Queue
Facility Study
IA Status
COD target: 2018
Total Duration
3y 9m
Schedule
95 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-07-01
BPA-G0501 is a proposed generation project located in Klamath County, Oregon, with a total capacity of 1100 MW. The project, which utilizes gas-fired technology, is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 13, 2014. The proposed commercial operation date (COD) is July 1, 2018. The point of interconnection (POI) is the Captain Jack 500 kV Substation, and the project's interconnection status is currently in the Facility Study phase.
The development has been the subject of recent news coverage related to grid infrastructure. The project is composed of a single 1100 MW gas-fired component.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Captain Jack 500 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31