BPA-G0513
20 MW generation in Morrow, OR · In queue since September 2015 · Proposed COD December 2016
20 MW
Capacity
1
Components
Solar
10y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2016
Total Duration
1y 3m
Schedule
114 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2016-12-31
BPA-G0513 is a proposed solar generation project with a total capacity of 20 MW, located in Morrow County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of September 18, 2015. The proposed commercial operation date is December 31, 2016.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is on a 115 kV line tap proximate to Tower Road Switch Station.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
115 kV line tap proximate to Tower Road Switch Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.