BPA-G0516
20 MW generation in Sherman, OR · In queue since October 2015 · Proposed COD October 2016
20 MW
Capacity
1
Components
Solar
10y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2016
Total Duration
1 year
Schedule
117 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2016-10-01
The proposed BPA-G0516 project is a 20 MW solar generation project located in Sherman County, Oregon. Interconnecting to Bonneville Power Administration's (BPA) grid at Iberdrola's Schoolhouse Substation at 230 kV, the project entered the BPA interconnection queue on October 20, 2015. The proposed commercial operation date is October 1, 2016, and the interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 20 MW of solar photovoltaic generation capacity. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Iberdrola's Schoolhouse Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.