BPA-G0523
13 MW generation in Wasco, OR · In queue since January 2016 · Proposed COD December 2018
13 MW
Capacity
1
Components
Solar
10y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2018
Total Duration
2y 11m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-12-31
The proposed BPA-G0523 project is a 13 MW solar generation project located in Wasco County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an original queue entry date of January 7, 2016. The proposed commercial operation date is December 31, 2018.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the BPA Maupin 69 kV Substation. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA Maupin 69 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.