BPA-G0524
20 MW generation in Wasco, OR · In queue since January 2016 · Proposed COD December 2018
20 MW
Capacity
1
Components
Solar
10y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2018
Total Duration
2y 11m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-12-31
The proposed BPA-G0524 project is a 20 MW solar generation development in Wasco County, Oregon. Interconnecting to the Bonneville Power Administration (BPA) grid, the project entered the BPA queue on January 7, 2016, with a proposed commercial operation date of December 31, 2018. The point of interconnection is planned to be within two miles of Wasco Electric Coop's 69 kV Tygh Valley Substation, either via a tap or a new substation.
The interconnection agreement for the BPA-G0524 project is currently listed as "In Progress" with an unknown study status.
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Within 2 miles of Wasco Electric Coop's 69 kV Tygh Valley Substation (Tap or new substation)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.