BPA-G0532
100 MW generation in Morrow, OR · In queue since March 2016 · Proposed COD June 2017
100 MW
Capacity
1
Components
Solar
10y 2m
In Queue
Facility Study
IA Status
COD target: 2017
Total Duration
1y 3m
Schedule
108 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2017-06-30
The proposed BPA-G0532 project is a 100 MW solar generation project located in Morrow County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of March 18, 2016. The proposed commercial operation date is June 30, 2017.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is on a 115 kV line tap proximate to Tower Road Switch Station. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
A 115 kV line tap proximate to Tower Road Switch Station.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.