BPA-G0535
210 MW generation in Walla Walla, WA · In queue since May 2016 · Proposed COD July 2031
210 MW
Capacity
1
Components
Hydro
10 years
In Queue
Facility Study
IA Status
COD target: 2031
Total Duration
15y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-07-25
BPA-G0535 is a proposed 210 MW hydroelectric generation project located in Walla Walla County, Washington. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of May 5, 2016. Its proposed commercial operation date is July 25, 2031. The project's interconnection status is currently in the Facility Study phase.
The development project consists of 210 MW of hydroelectric capacity. It is listed under the utility and entity of Bonneville Power Administration (BPA).
Generated from interconnection queue and public data sources
State
WA
County
Walla Walla
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0535