BPA-G0537
20 MW generation in Harney, OR · In queue since May 2016 · Proposed COD April 2019
20 MW
Capacity
1
Components
Solar
10 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Total Duration
2y 11m
Schedule
86 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-04-01
The proposed BPA-G0537 project is a 20 MW solar generation facility located in Harney County, Oregon. The project, under consideration by the Bonneville Power Administration (BPA), consists of 20 MW of solar photovoltaic generation. It is in the BPA interconnection queue as of May 12, 2016, with a proposed commercial operation date of April 1, 2019.
The interconnection status is listed as "In Progress (unknown study)". The point of interconnection is planned as a line tap into the BPA Harney-Brasada 115 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Harney
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Line tap into BPA Harney-Brasada 115 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN