BPA-G0543
350 MW generation in Umatilla, OR · In queue since June 2016 · Proposed COD December 2019
350 MW
Capacity
1
Components
Wind
9y 11m
In Queue
Facility Study
IA Status
COD target: 2019
Total Duration
3y 6m
Schedule
77 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-12-31
BPA-G0543 is a proposed wind generation project with a total capacity of 350 MW. The project is located in Umatilla County, Oregon, and is being developed within the Bonneville Power Administration (BPA) service area. It entered the BPA interconnection queue on June 6, 2016, with a proposed commercial operation date of December 31, 2019.
As of its latest queue status, the project is in the Facility Study phase of the interconnection process. The point of interconnection (POI) is specified as either BPA's McNary 230 kV substation or the proposed Stanfield Substation at 230 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Umatilla
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's McNary 230 kV or the proposed Stanfield Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0543