BPA-G0566
646 MW generation in Lincoln, MT · In queue since June 2017 · Proposed COD September 2022
646 MW
Capacity
1
Components
Hydro
8y 11m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
5y 3m
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-09-30
BPA-G0566 is a proposed hydroelectric generation project with a total capacity of 646 MW, located in Lincoln County, Montana. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 5, 2017. The proposed commercial operation date is September 30, 2022. The project's interconnection status is currently in the Facility Study phase.
The development project consists solely of hydroelectric generation, with all 646 MW of capacity attributed to this technology. It is listed under the utility and entity of Bonneville Power Administration (BPA).
Generated from interconnection queue and public data sources
State
MT
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0566