BPA-G0570
20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019
20 MW
Capacity
1
Components
Solar
8y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Total Duration
1y 11m
Schedule
84 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-06-01
The proposed BPA-G0570 project is a 20 MW solar generation project located in Lake County, Oregon. Interconnecting to the Bonneville Power Administration (BPA) grid, the project entered the BPA queue on July 31, 2017, with a proposed commercial operation date of June 1, 2019.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is a tap off BPA's 115 kV line within 10 miles of Midstate Electric's Fort Rock 115 kV Substation.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Tap off BPA's 115 kV line within 10 miles of Midstate Electric's Fort Rock 115 kV Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0570