BPA-G0571
20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019
20 MW
Capacity
1
Components
Solar
8y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Total Duration
1y 11m
Schedule
84 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-06-01
BPA-G0571 is a proposed 20 MW solar generation project located in Lake County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of July 31, 2017. The proposed commercial operation date is June 1, 2019.
The interconnection agreement (IA) status for BPA-G0571 is listed as "In Progress (unknown study)". The point of interconnection (POI) is a tap off BPA's 115 kV line within 10 miles of Midstate Electric's Fort Rock 115 kV Substation.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Tap off BPA's 115 kV line within 10 miles of Midstate Electric's Fort Rock 115 kV Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0571