BPA-G0572
20 MW generation in Lake, OR · In queue since July 2017 · Proposed COD June 2019
20 MW
Capacity
1
Components
Solar
8y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Total Duration
1y 11m
Schedule
84 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-06-01
The proposed project BPA-G0572 is a 20 MW solar generation project located in Lake County, Oregon. Interconnection is being managed through the Bonneville Power Administration (BPA) queue, with an initial queue entry date of July 31, 2017. The proposed commercial operation date is June 1, 2019.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is Midstate Electric's Fort Rock 115 kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Midstate Electric's Fort Rock 115 kV Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0572