BPA-G0585
313 MW generation in Klickitat, WA · In queue since March 2018 · Proposed COD July 2021
313 MW
Capacity
1
Components
Wind
8y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3y 4m
Schedule
59 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-07-01
BPA-G0585 is a proposed wind generation project with a total capacity of 313 MW. The project is located in Klickitat County, Washington, and is interconnected to the Bonneville Power Administration (BPA) grid. The point of interconnection is the McNary-John Day 500kV Tap, also known as BPA's "G0585 Substation".
The project entered the BPA interconnection queue on March 19, 2018, with a proposed commercial operation date of July 1, 2021. The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
McNary-John Day 500kV Tap (BPA's "G0585 Substation")
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.