BPA-G0586
100 MW generation in Klickitat, WA · In queue since April 2018 · Proposed COD June 2022
100 MW
Capacity
1
Components
Solar
8y 1m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
4y 2m
Schedule
47 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-06-15
The proposed BPA-G0586 project is a 100 MW solar generation project located in Klickitat County, Washington. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of April 6, 2018. Its proposed commercial operation date is June 15, 2022.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is BPA's Spring Creek 230 kV Substation.
Generated from interconnection queue and public data sources
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's Spring Creek 230 kV Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0586