BPA-G0594
1 MW generation in Lane, OR · In queue since July 2018 · Proposed COD September 2018
1 MW
Capacity
1
Components
Solar
7y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2018
Total Duration
2 months
Schedule
93 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-09-21
BPA-G0594 is a proposed 1 MW solar generation project located in Lane County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of July 18, 2018. The proposed commercial operation date is September 21, 2018.
The interconnection agreement (IA) status for BPA-G0594 is listed as "In Progress (unknown study)". The point of interconnection (POI) is with EWEB's system, with the exact location to be determined.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
EWEB's system. Exact location TBD.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0594