BPA-G0596
112 MW hybrid in Yakima, WA · In queue since July 2018 · Proposed COD December 2021
112 MW
Capacity
2
Components
Solar + Battery
7y 10m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
3y 5m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
BPA-G0596 is a proposed 112 MW hybrid solar and battery project located in Yakima County, Washington. The project consists of an 80 MW solar array coupled with a 32 MW battery energy storage system. It is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of July 31, 2018.
The proposed commercial operation date for BPA-G0596 is December 31, 2021. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is BPA's Midway - Moxee 115 kV line.
Generated from interconnection queue and public data sources
State
WA
County
Yakima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's Midway - Moxee 115 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.