BPA-G0598
223 MW hybrid in Klickitat, WA · In queue since August 2018 · Proposed COD December 2021
223 MW
Capacity
2
Components
Solar + Battery
7y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3y 4m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
BPA-G0598 is a proposed 223 MW hybrid solar and battery project located in Klickitat County, Washington. The project, consisting of 160 MW of solar generation and a 63 MW battery energy storage system, is interconnected to Bonneville Power Administration's (BPA) North Bonneville - Midway 230 kV line.
The project is currently active in the BPA interconnection queue, with an entry date of August 1, 2018. The proposed commercial operation date is December 31, 2021, and the interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's North Bonneville - Midway 230 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.