Project BPA-G0615 — Project Summary

Queue ID
BPA-G0615
Capacity
1200 MW
Technology
Solar+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
Facility Study

BPA-G0615

BPA-G0615BetaActiveSolarBatteryBPALBNL

1,200 MW hybrid in Sherman, OR · In queue since February 2019 · Proposed COD December 2021

1,200 MW

Capacity

2

Components

Solar + Battery

7y 3m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection

Total Duration

2y 10m

Schedule

53 months past proposed COD

Facilities Study50%
Queue EntryFeb 21, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Technology
Solar800 MW · 67%
Battery400 MW · 33%
About

BPA-G0615 is a proposed 1200 MW hybrid Solar+Battery project located in Sherman County, Oregon. The project, which appeared in the news recently, consists of an 800 MW solar array and a 400 MW battery energy storage system. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of February 21, 2019.

The proposed commercial operation date is December 31, 2021. The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Sherman

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.