BPA-G0615
1,200 MW hybrid in Sherman, OR · In queue since February 2019 · Proposed COD December 2021
1,200 MW
Capacity
2
Components
Solar + Battery
7y 3m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
2y 10m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
BPA-G0615 is a proposed 1200 MW hybrid Solar+Battery project located in Sherman County, Oregon. The project, which appeared in the news recently, consists of an 800 MW solar array and a 400 MW battery energy storage system. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of February 21, 2019.
The proposed commercial operation date is December 31, 2021. The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Slatt - Buckley No 1 500 kV transmission line, approximately 10 miles from Buckley Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.