BPA-G0617
300 MW hybrid in Sherman, OR · In queue since March 2019 · Proposed COD August 2022
300 MW
Capacity
2
Components
Solar + Battery
7y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 5m
Schedule
46 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-08-01
BPA-G0617 is a proposed 300 MW hybrid Solar+Battery project located in Sherman County, Oregon. The development project consists of 200 MW of solar capacity and 100 MW of battery energy storage. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of March 22, 2019.
The proposed commercial operation date is August 1, 2022. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the John Day No 2 230 kV transmission line or Biglow Canyon Substation.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
John Day No 2 230 kV transmission line or Biglow Canyon Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0617