BPA-G0625
191 MW generation in Morrow, OR · In queue since June 2019 · Proposed COD December 2020
191 MW
Capacity
1
Components
Solar
6y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Total Duration
1y 6m
Schedule
65 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-31
BPA-G0625 is a proposed 191 MW solar generation project located in Morrow County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 5, 2019. The proposed commercial operation date is December 31, 2020. Interconnection agreement status is listed as "In Progress (unknown study)".
The project, which consists of 191 MW of solar photovoltaic generation, intends to interconnect at BPA's McNary Substation.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's McNary Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.