BPA-G0637
190 MW storage in Klickitat, WA · In queue since January 2020 · Proposed COD December 2022
190 MW
Capacity
1
Components
Battery
6y 4m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
2y 11m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
BPA-G0637 is a proposed 190 MW battery storage project located in Klickitat County, Washington. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of January 28, 2020. The proposed commercial operation date is December 31, 2022.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Knight 500 kV Substation.
Generated from interconnection queue and public data sources
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Knight 500 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0637