BPA-G0642
600 MW storage in Crook, OR · In queue since February 2020 · Proposed COD June 2025
600 MW
Capacity
1
Components
Battery
6y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
5y 4m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
BPA-G0642 is a proposed 600 MW battery storage project located in Crook County, Oregon. The project, under development within the Bonneville Power Administration (BPA) region, entered the BPA interconnection queue on February 24, 2020. The proposed commercial operation date is June 1, 2025.
The interconnection agreement for BPA-G0642 is currently listed as "In Progress" with an unknown study status. The point of interconnection is the Ponderosa 230 kV substation.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ponderosa 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0642