Project BPA-G0643 — Project Summary

Queue ID
BPA-G0643
Capacity
600 MW
Technology
Battery
Status
active
Location
Crook, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0643

BPA-G0643BetaActiveBatteryBPALBNL

600 MW storage in Crook, OR · In queue since February 2020 · Proposed COD June 2024

600 MW

Capacity

1

Components

Battery

6y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

4y 4m

Schedule

23 months past proposed COD

In Study38%
Queue EntryFeb 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-01

About

BPA-G0643 is a proposed 600 MW battery storage project located in Crook County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of February 24, 2020. The proposed commercial operation date is June 1, 2024.

The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ponderosa 230 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Crook

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Ponderosa 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G0643