BPA-G0657
1,000 MW hybrid in Klamath, OR · In queue since September 2020 · Proposed COD January 2027
1,000 MW
Capacity
2
Components
Solar + Battery
5y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-01
BPA-G0657 is a proposed 1000 MW hybrid solar and battery project located in Klamath County, Oregon. The development project, which appeared in the Bonneville Power Administration (BPA) interconnection queue on September 16, 2020, consists of 500 MW of solar generation and 500 MW of battery energy storage. The proposed commercial operation date is January 1, 2027.
The project's interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the La Pine - Chiloquin No 1 line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
La Pine - Chiloquin No 1 line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.