BPA-G0660
300 MW hybrid in Grant, WA · In queue since November 2020 · Proposed COD October 2024
300 MW
Capacity
2
Components
Solar + Battery
5y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 11m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
BPA-G0660 is a proposed 300 MW hybrid Solar+Battery project located in Grant County, Washington. The development project consists of a 200 MW solar component and a 100 MW battery energy storage system. It is listed in the Bonneville Power Administration interconnection queue with an entry date of November 5, 2020, and a proposed commercial operation date of October 1, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The project's points of interconnection are Grand Coulee - Rocky Ford 230 kV and Grand Coulee - Potholes 230 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
POI 1: Grand Coulee - Rocky Ford 230 kV POI 2: Grand Coulee - Potholes 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0660