BPA-G0678
1,200 MW generation in Morrow, OR · In queue since June 2021 · Proposed COD December 2024
1,200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 6m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
The proposed project BPA-G0678 is a 1200 MW solar generation project located in Morrow County, Oregon. Interconnecting to the Bonneville Power Administration (BPA) grid at the Longhorn substation 230 kV point of interconnection, the project entered the BPA interconnection queue on June 17, 2021, with a proposed commercial operation date of December 31, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 1200 MW of solar capacity. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Longhorn substation 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31