BPA-G0683
233 MW generation in Benton, WA · In queue since July 2021 · Proposed COD December 2026
233 MW
Capacity
1
Components
Wind
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The proposed project BPA-G0683 is a 233 MW wind generation project located in Benton County, Washington. The project was entered into the Bonneville Power Administration (BPA) interconnection queue on July 19, 2021, with a proposed commercial operation date of December 31, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 233 MW of wind generation capacity. The point of interconnection (POI) is the Wautoma 500 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Wautoma 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.