BPA-G0686
127.5 MW generation in Benton, WA · In queue since August 2021 · Proposed COD July 2028
127.5 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-03
BPA-G0686 is a proposed solar generation project with a total capacity of 127.5 MW, located in Benton County, Washington. The project was entered into the Bonneville Power Administration interconnection queue on August 13, 2021, with a proposed commercial operation date of July 3, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)".
The development project consists of 127.5 MW of solar photovoltaic generation. The point of interconnection is the Benton No 2 115 kV line. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Benton No 2 115 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0686