BPA-G0687
900 MW generation in Sherman, OR · In queue since August 2021 · Proposed COD December 2024
900 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
BPA-G0687 is a proposed 900 MW solar generation project located in Sherman County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of August 25, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is near Grass Valley in Sherman County, Oregon, at coordinates 45.371967, -120.707373.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
45.371967, -120.707373 - Grass valley Sherman County OR
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.