BPA-G0695
3,600 MW hybrid in Crook, OR · In queue since September 2021 · Proposed COD December 2028
3,600 MW
Capacity
3
Components
Biofuel + Battery + Pumped Storage
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed project BPA-G0695 is a 3600 MW hybrid energy project located in Crook County, Oregon. Interconnecting to the Bonneville Power Administration (BPA) grid at the Ponderosa Substation 500 kV, the project consists of 1200 MW of Biofuel, 1200 MW of Battery storage, and 1200 MW of Pumped Storage. The project entered the BPA interconnection queue on September 22, 2021, with a proposed commercial operation date of December 1, 2028.
The interconnection agreement is currently listed as "In Progress (unknown study)". This development project has been mentioned in recent news coverage related to grid infrastructure.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ponderosa Substation 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31