BPA-G0706
100 MW generation in Morrow, OR · In queue since October 2021 · Proposed COD December 2024
100 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
BPA-G0706 is a proposed 100 MW solar generation project located in Morrow County, Oregon. The project is in the Bonneville Power Administration interconnection queue, with an entry date of October 20, 2021, and a proposed commercial operation date of December 31, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project consists of 100 MW of solar photovoltaic generation. The point of interconnection is the Slatt Substation. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Slatt Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0706