BPA-G0707
60 MW storage in Morrow, OR · In queue since October 2021 · Proposed COD December 2023
60 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
2y 2m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
BPA-G0707 is a proposed 60 MW battery storage project located in Morrow County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of October 26, 2021. The proposed commercial operation date is December 1, 2023.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the BPA’s Boardman – Alkali 115 kV transmission line.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA_x0019_s Boardman _x0013_ Alkali 115 kV transmission line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0707