BPA-G0712
448 MW generation in Sherman, OR · In queue since November 2021 · Proposed COD December 2025
448 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 1m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
BPA-G0712 is a proposed solar generation project with a total capacity of 448 MW, located in Sherman County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 23, 2021, and a proposed commercial operation date of December 31, 2025. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection (POI) is listed as coordinates 45.67752437675481, -120.7374771, near Wasco in Sherman County, Oregon. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
45.67752437675481, -120.7374771 - Wasco Sherman County OR
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.