BPA-G0714
400 MW hybrid in Sherman, OR · In queue since December 2021 · Proposed COD December 2025
400 MW
Capacity
2
Components
Solar + Battery
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
BPA-G0714 is a proposed 400 MW hybrid solar and battery project located in Sherman County, Oregon. The project, consisting of 200 MW of solar generation and 200 MW of battery energy storage, is in the Bonneville Power Administration (BPA) interconnection queue. The queue entry date is December 2, 2021, with a proposed commercial operation date of December 1, 2025.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Buckley 500 kV Substation.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Buckley 500 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.