BPA-G0721
13.6 MW generation in Benton, WA · In queue since December 2021 · Proposed COD November 2024
13.6 MW
Capacity
1
Components
Wind
4y 5m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-15
BPA-G0721 is a proposed wind generation project with a total capacity of 13.6 MW. The project is located in Benton County, Washington, and is being managed within the Bonneville Power Administration (BPA) interconnection queue. The project entered the queue on December 22, 2021, and has a proposed commercial operation date of November 15, 2024. Its interconnection status is currently in the Facility Study phase.
The point of interconnection (POI) for BPA-G0721 is the Franklin - McNary 230 kV line, at the new Bofer Canyon Substation. The project consists solely of wind generation, with the full 13.6 MW capacity attributed to this technology.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Franklin - McNary 230 kV line, at the new Bofer Canyon Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.