BPA-G0725
600 MW storage in Coos, OR · In queue since January 2022 · Proposed COD December 2027
600 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-10
BPA-G0725 is a proposed 600 MW battery storage project located in Coos County, Oregon. The project, which is in the Bonneville Power Administration (BPA) interconnection queue, entered the queue on January 26, 2022, with a proposed commercial operation date of December 10, 2027. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 600 MW of battery storage capacity. The point of interconnection is the Fairview 230 kV Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Coos
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Fairview 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.