BPA-G0728
420 MW hybrid in Sherman, OR · In queue since February 2022 · Proposed COD December 2026
420 MW
Capacity
2
Components
Wind + Battery
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
BPA-G0728 is a proposed hybrid wind and battery project with a total capacity of 420 MW, located in Sherman County, Oregon. The project consists of 210 MW of wind generation and 210 MW of battery storage. Interconnection is being requested through the Bonneville Power Administration (BPA) queue, with an entry date of February 4, 2022, and a proposed commercial operation date of December 1, 2026.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Jones Canyon to Tumble Creek section of Jones Canyon-Santiam No 1 230 kV line; Ashe to Marian No 2 500 kV line; or Slatt to Buckley No 1 500 kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Jones Canyon to Tumble Creek section of Jones Canyon-Santiam No 1 230 kV line; Ashe to Marian No 2 500 kV line; or Slatt to Buckley No 1 500 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.