Project BPA-G0728 — Project Summary

Queue ID
BPA-G0728
Capacity
420 MW
Technology
Wind+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0728

BPA-G0728BetaActiveWindBatteryBPALBNL

420 MW hybrid in Sherman, OR · In queue since February 2022 · Proposed COD December 2026

420 MW

Capacity

2

Components

Wind + Battery

4y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

4y 10m

In Study38%
Queue EntryFeb 4, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Technology
Wind210 MW · 50%
Battery210 MW · 50%
About

BPA-G0728 is a proposed hybrid wind and battery project with a total capacity of 420 MW, located in Sherman County, Oregon. The project consists of 210 MW of wind generation and 210 MW of battery storage. Interconnection is being requested through the Bonneville Power Administration (BPA) queue, with an entry date of February 4, 2022, and a proposed commercial operation date of December 1, 2026.

The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Jones Canyon to Tumble Creek section of Jones Canyon-Santiam No 1 230 kV line; Ashe to Marian No 2 500 kV line; or Slatt to Buckley No 1 500 kV line. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Sherman

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Jones Canyon to Tumble Creek section of Jones Canyon-Santiam No 1 230 kV line; Ashe to Marian No 2 500 kV line; or Slatt to Buckley No 1 500 kV line.

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G0728