BPA-G0732
400 MW hybrid in Benton, WA · In queue since March 2022 · Proposed COD April 2027
400 MW
Capacity
2
Components
Solar + Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
BPA-G0732 is a proposed 400 MW hybrid solar and battery project located in Benton County, Washington. The project, which consists of 200 MW of solar generation and 200 MW of battery energy storage, is in the Bonneville Power Administration (BPA) interconnection queue. The queue entry date is March 11, 2022, with a proposed commercial operation date of April 15, 2027.
The interconnection agreement (IA) status for BPA-G0732 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Wautoma 500 kV substation.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Wautoma 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0732