BPA-G0733
30 MW storage in Benton, WA · In queue since March 2022 · Proposed COD October 2025
30 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-31
BPA-G0733 is a proposed 30 MW battery storage project located in Benton County, Washington. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of March 15, 2022. The proposed commercial operation date is October 31, 2025.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is yet to be determined. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
TBD
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0733