BPA-G0734
20 MW storage in Benton, WA · In queue since March 2022 · Proposed COD November 2024
20 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 8m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-15
BPA-G0734 is a proposed 20 MW battery storage project located in Benton County, Washington. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of March 15, 2022, and a proposed commercial operation date of November 15, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection (POI) is a new 230 kV substation that will tap the Franklin-McNary 230kV Transmission Line. The project consists of a single 20 MW battery component.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
New 230 kV Substation that will tap the Franklin-McNary 230kV Transmission Line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0734