BPA-G0744
400 MW hybrid in Grant, WA · In queue since May 2022 · Proposed COD December 2026
400 MW
Capacity
2
Components
Solar + Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
BPA-G0744 is a proposed 400 MW hybrid Solar+Battery project located in Grant County, Washington. The project consists of 200 MW of solar generation and a 200 MW battery energy storage system. It is listed in the Bonneville Power Administration interconnection queue with an entry date of May 24, 2022, and a proposed commercial operation date of December 30, 2026.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is identified as 1. Vantage-Hanford #1 500 kV line 2. Corridor of the 230kV Midway- Rocky Ford and Midway-Potholes 230kV transmission lines.
Generated from interconnection queue and public data sources
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
1. Vantage-Hanford #1 500 kV line 2. Corridor of the 230kV Midway- Rocky Ford and Midway-Potholes 230kV transmission lines
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0744